Abeokuta, April 15, 2019 The Ogun Government on Monday said that it spent N9.348billion between January and March on the construction and rehabilitation of some roads across its three senatorial districts

 

The Permanent Secretary in the State Ministry of Works and Infrastructure, Mr  Kayode Ademolake, said this.

 

It was when he was presenting the budget performance of the ministry before the House of Assembly Committee on Finance and Appropriation at the Assembly complex in Abeokuta.

 

The House committee has Mr Victor Fasanya as its chairman.

 

 

Other are: the Ilo-Awela Road that was at 75 per cent completion, OGTV-Brewery Road at 75 per cent completion and the Ejinrin-Oluwalogbon Road at 90 per cent completion.

 

He said that construction works on the Ojere-Adatan Road  had reached  86 per cent completion and the construction of the Abule Ekun River Bridge had  reached  90 per cent completion.

 

Ademolake also said that the construction of the  pedestrian bridges at Mowe, Ibafo and Panseke were  90 per cent completion.

 

The permanent secretary also reviewing the budget performance of the Ministry during the period stated that the Ministry raked in N312.5 million.

 

 

He added that the construction of additional secretariat building (Block E) was ongoing within the state secretariat.

 

The permanent secretary said that the Ministry equally established a material testing laboratory through the Public Private Partnership agreement.

 

He said that it also constructed befitting modern markets, residential buildings and shops in line with the urban renewal programme of the state government.